The General procedure of connection to electric networks

 

SUBMISSION
APPLICATIONS AND PACKAGE
DOCUMENTS

CONSIDERATION
APPLICATIONS TO 6
WORKING DAYS

DIRECTION
PROJECTAND CONTRACT
UP TO 15 WORKING DAYS

CONSIDERATION
AND THE CONCLUSION
CONTRACT UP TO 30
WORKING DAYS


OF RECEIPT
CONTRACT AND TECHNICAL
CONDITIONS

EVENTS
TECHNOLOGICAL
CONNECTION
6 MONTHS


FROM THE DATE OF CONCLUSION
CONTRACT

 

The ACTUAL
ACCESSION AND
The SIGNING
ACTS




 

 

 

 Required documents

  1. A copy of the document confirming the right of ownership or other legal basis to object of capital construction (non-residential premises in such objects of capital construction) and (or) a land plot, on which there are (will be) objects of the applicant.
  2. The power of attorney or other documents confirming powers of the representative of the Applicant, submitting and receiving documents, in case the application is submitted to the network organization representative of the applicant.
  3. Layout of power receiving devices (power plant) to be attached to electric networks of the network organization.
  4. One-linear scheme of electric networks of the applicant, which are attached to electric networks of the network organization, the nominal voltage which is 35 kV and above, indicating the possibility of reservation from own sources of supply (including backup for their own needs) and the possibility of switching loads (generation) in internal networks of the Applicant (if available).
  5. The list and capacity of power receivers that can be connected to devices of emergency control automatics.